Start with a BOQ every bidder can price the same way
Most disputes in fire safety projects trace back to a vague bill of quantities. "Fire door – 10 nos" will attract ten very different products. Each BOQ line should state:
- Product and model type (for example single-leaf fire-rated door, double-door fire hose cabinet, 5 kg CO2 extinguisher).
- Performance requirement: fire rating in minutes, extinguisher rating, listing requirement (for example UL-listed hardware).
- Size and quantity, with drawings or a schedule for doors, cabinets and racks.
- Material and finish: sheet type and thickness, stainless grade where relevant, powder-coat colour.
- Accessories: closers, panic devices, locks, vision panels, hoses, nozzles, brackets.
- Scope: supply only, supply and install, or supply, install, test and commission.
- Documents required with the bid and at handover.
If you do not have engineering support to prepare this, a fire protection engineer can produce the specification and BOQ before you tender.
Documents to request from every bidder
| Document | What it proves | Red flag |
|---|---|---|
| Product datasheet | Exact model, dimensions, materials, ratings | Generic brochure with no model numbers |
| Test report or certificate (for example fire test of a door) | The tested design achieved the claimed rating | Report for a different model, size or core |
| Listing reference (for example UL) | Product is listed by a recognised body | Logo on brochure but no listing reference |
| Country of origin and manufacturer details | Traceability | Unwilling to name the manufacturer |
| Shop drawings (for fabricated items) | What will actually be built | Drawings only after payment |
| Warranty terms | Who fixes what, for how long | Verbal warranty only |
| Installation method statement | How the work will be done safely | No method, no supervision named |
| Past similar supply references | Ability to deliver this scope | No contactable references |
| Trade licence and tax documents | Legal entity you can contract with | Mismatch between company names |
Ask for the documents with the bid, not after award. A supplier who has the evidence can send it quickly.
Verifying listings and test reports
UL listings. UL publishes certification information in its online directory (Product iQ, linked from ul.com). Search the manufacturer and product category and confirm the model in your quotation appears. A UL logo printed on packaging is not the same as a listing for the specific model.
Test reports. For a fire-rated door, check that the report names the laboratory, the standard, the door configuration (single or double leaf), the core material, the leaf thickness, the hardware tested and the fire rating achieved. A report for a smaller door or different core does not automatically cover a larger or different one. Where a report or certificate is issued by a local institution, such as a BUET test certificate for a door, ask for a copy and confirm the model and date.
Extinguishers. Check the rating and standard on the label, weigh a sample and confirm the manufacturing date. Counterfeit and underfilled units are a known problem in low-priced stock.
When documents do not match the product offered, ask for clarification in writing before going further.
Sample and factory inspection
For manufactured items such as fire-rated doors, hose cabinets, DB boxes, lockers and racks, a sample and a factory visit tell you more than a brochure:
- Sheet thickness: measure with a calliper or micrometer against the datasheet.
- Welding: continuous, even welds where specified; no burn-through or spatter left on visible faces.
- Surface preparation and coating: ask how steel is de-rusted and pre-treated before powder coating; check coating adhesion and evenness.
- Hardware: brand, model and listing of hinges, closers and panic devices.
- Dimensions and squareness: measure diagonals of door frames and cabinets.
- Production capacity: can the factory deliver your quantity on your timeline?
Safety Plus fabricates in mild steel or stainless steel at its Demra factory, with chemical de-rusting, zinc phosphate coating and oven-baked powder paint. Whichever manufacturer you evaluate, ask to see a sample and the process steps on the shop floor. Our article on powder coating and zinc phosphate explains what to look for.
Delivery, installation and commissioning scope
Write down who does what. Common gaps:
- Civil works: who cuts openings, grouts door frames, fixes cabinets into walls and makes good?
- Interfaces: who connects the door holder to the alarm, or the hose cabinet to the riser?
- Site logistics: delivery to floor, storage on site, crane or lift use, working hours.
- Testing: who tests, to what standard, with what witness, and who pays for re-tests?
- Training and handover: operation and maintenance manuals, as-built drawings, test certificates, spare keys.
- Exclusions: insist the bid lists them clearly.
For systems such as FM200 or CO2 suppression, require a commissioning test and handover file as part of the scope.
Payment milestones, warranty and comparing bids
A typical milestone structure links payment to verifiable progress:
| Milestone | Evidence |
|---|---|
| Advance (if any) | Signed contract, approved shop drawings |
| Delivery | Delivery note, inspection on arrival against BOQ |
| Installation | Installation completed and checked by your engineer |
| Testing and commissioning | Signed test reports |
| Retention release | End of defects period, all snags closed |
Keep warranty start dates tied to handover, not delivery.
Score bids, do not just rank prices. A simple weighting such as compliance with specification (30%), quality of evidence (20%), scope completeness (20%), after-sales and warranty (10%) and price (20%) helps you choose the bid with the lowest real cost. Adjust weights to your project, but agree them before you open the prices. For more on choosing suppliers, see how to choose a fire safety company and made in Bangladesh vs imported products.
After award: handover and after-sales
- Receive the handover file: datasheets, test reports, warranty certificates, as-built drawings, maintenance schedule.
- Register all equipment in an asset list with locations and serial numbers.
- Agree the maintenance or inspection contract, response time and spares.
- Schedule the first inspection, for example extinguisher checks and pump tests.
Safety Plus supplies manufactured products on a quotation basis. Browse fire rated doors, fire hose cabinets or fire safety equipment, then send your BOQ through request a quote.
Frequently asked questions
What documents should a fire safety supplier provide with a quotation?
At minimum: product datasheets with model numbers, test reports or listing references for rated products, warranty terms, installation scope and exclusions, and company registration documents.
How do I check whether a product is really UL listed?
Search UL's online certification directory, Product iQ, linked from ul.com, for the manufacturer and product category, and confirm the exact model appears. A printed logo on its own is not proof.
Should we buy fire safety equipment on lowest price?
Lowest price is risky if bids are not like-for-like. Score bids on compliance, evidence, scope and after-sales as well as price, and make sure every bidder priced the same BOQ.
What is a sensible retention for fire safety works?
Many buyers keep a retention until the end of the defects liability period so any snags are fixed. The amount and duration should be agreed in the contract before work starts.
Is a factory visit really necessary?
For manufactured items like fire doors, hose cabinets and racks it is strongly recommended, because it shows sheet thickness, welding quality, coating process and production capacity directly.